Monday, April 13, 2015 – Bay Street from Monroe to Jackson St (areas with the new brick such as this street will be closed in sections during the day and immediately re-opened as each section is sanded)
Tuesday, April 14, 2015 – Jackson St from Bay St to Second St (same as above)
Wednesday, April 15, 2015 – Dean St from Bay to First St and Broadway from First St to Second St (same as above)
Thursday, April 16, 2015 – Hendry St from Bay to First St (areas with the old historic bricks such as this section will remain closed for 24 hours after the sanding is complete to allow the sand to harden)
Monday, April 20, 2015 – Hendry St from First St to Main St. (same as above)
Tuesday, April 21, 2015 – First St from Monroe to Dean St (same as above)
Wednesday, April 22, 2015 – First St from Dean St to Hendry St (same as above)
Thursday, April 23, 2015 – First St from Hendry St to Jackson St (same as above)
Friday, April 24, 2015 – First St from Jackson St to Lee St (same as above)
Monday, April 27, 2015 – West half of Main St from Monroe to Broadway (same as above)
Tuesday, April 28, 2015 – East half of Main St from Monroe to Broadway (same as above)
Wednesday, April 29, 2015 – Main St from Broadway to Hendry St (same as above)
Thursday, April 30, 2015 – Main St from Hendry St to Jackson St (same as above)
Saturday, May 2, 2015 – Hendry St from Main St to Second St (same as above)